UTE Goiânia II
Construction year: 2008
Location: Aparecida de Goiânia/GO
Cliente: Telemenia LTDA
Israeli group Telemenia Thermoelectric power plant with 140MV of power. Plant with 88 generators and more than 1.800 tons of equipment installed. Storage tanks for over 3,100.000 liters of diesel. Water tank of over 200,000 liters for firefighting. Power plant with capacity to supply a city of about 500,000 inhabitants.
Built Area: 5,975.00 m²
Site Area: 72,572.30 m²
Built Area: 5,975.00 m²